RAB Tempat api | |||||||
Ukuran 6 x 2.5 | |||||||
No | Data | Vol | Satuan | Harga | Jumlah | Balance | Keterangan Bahan |
1 | Semen | 15 | Zak | 52,000 | 780,000 | 780,000 | |
2 | Pasir | 1 | Truk | 950,000 | 950,000 | 1,730,000 | |
3 | Batako | 350 | Buah | 2,400 | 840,000 | 2,570,000 | |
10 | Paku | 1 | Kg | 18,000 | 18,000 | 2,588,000 | |
11 | Hollow 4x4 | 6 | Batang | 125,000 | 750,000 | 3,338,000 | |
13 | Atap galvalum | 4 | Lembar | 195,000 | 780,000 | 4,118,000 |
Jumat, 17 Januari 2020
RAB Tempat api Ukuran 6 x 2.5
Kamis, 16 Januari 2020
RAB Kamar Mandi ngaben
RAB Kamar Mandi | |||||||
Ukuran 6.7 x 4.2 | |||||||
No | Data | Vol | Satuan | Harga | Jumlah | Balance | Keterangan Bahan |
1 | Semen | 65 | Zak | 52,000 | 3,380,000 | 3,380,000 | |
2 | Pasir | 3 | Truk | 950,000 | 2,850,000 | 6,230,000 | |
3 | Batako | 1500 | Buah | 2,400 | 3,600,000 | 9,830,000 | |
4 | Batu Kali | 2 | Truk | 1,200,000 | 2,400,000 | 12,230,000 | |
5 | Besi 10 sni | 12 | Buah | 65,000 | 780,000 | 13,010,000 | |
6 | Besi 6 sni | 6 | Buah | 32,000 | 192,000 | 13,202,000 | |
7 | Kawat Bendrat | 3 | Kg | 18,000 | 54,000 | 13,256,000 | |
8 | Papan Bekesting | 8 | Lbr | 105,000 | 840,000 | 14,096,000 | |
9 | Usuk Bekesting | 50 | Btg | 36,000 | 1,800,000 | 15,896,000 | |
10 | Paku | 5 | Kg | 18,000 | 90,000 | 15,986,000 | |
11 | Usuk Kruing | 30 | Batang | 95,000 | 2,850,000 | 18,836,000 | |
12 | Balok Kruing | 6 | Batang | 288,000 | 1,728,000 | 20,564,000 | |
13 | Atap galvalum | 9 | Lembar | 135,000 | 1,215,000 | 21,779,000 | |
14 | List Plang | 10 | M1 | 245,000 | 2,450,000 | 24,229,000 | |
15 | Bubungan | 40 | Buah | 8,500 | 340,000 | 24,569,000 | |
16 | Zink lengkap accessories | 4 | Unit | 675,000 | 2,700,000 | 27,269,000 | |
17 | Kloset duduk | 2 | Unit | 1,675,000 | 3,350,000 | 30,619,000 | |
18 | Urinal | 3 | Unit | 1,250,000 | 3,750,000 | 34,369,000 | |
19 | Pipa Air | 16 | Batang | 18,000 | 288,000 | 34,657,000 | |
20 | Sambungan sambungan | 24 | Set | 4,500 | 108,000 | 34,765,000 | |
21 | Lem Pipa | 2 | Kaleng | 38,000 | 76,000 | 34,841,000 | |
22 | Keran Air | 8 | Unit | 45,000 | 360,000 | 35,201,000 | |
23 | Keramik Lantai | 13 | M2 | 85,000 | 1,105,000 | 36,306,000 | |
24 | Keramik Dinding | 75 | M2 | 105,000 | 7,875,000 | 44,181,000 | |
25 | Keramik Meja dapur | 5 | Kg | 125,000 | 625,000 | 44,806,000 | |
26 | Keramik kamar mandi | 8 | M2 | 95,000 | 760,000 | 45,566,000 | |
27 | Kabel Listrik | 2 | Roll | 485,000 | 970,000 | 46,536,000 | |
28 | Fiting | 8 | Titik | 16,000 | 128,000 | 46,664,000 | |
29 | Lampu | 8 | Titik | 65,000 | 520,000 | 47,184,000 | |
30 | Saklar | 4 | Titik | 45,000 | 180,000 | 47,364,000 | |
31 | Stop kontak | 6 | Titik | 45,000 | 270,000 | 47,634,000 | |
32 | Pintu | 3 | Set | 985,000 | 2,955,000 | 50,589,000 | |
33 | Kusen kaca mati | 3 | set | 375,000 | 1,125,000 | 51,714,000 | |
34 | Septic tank Beton | 2 | Set | 985,000 | 1,970,000 | 53,684,000 | |
35 | Pipa 4 inchi | 4 | Batang | 365,000 | 1,460,000 | 55,144,000 | |
36 | Cat tembok | 5 | Kg | 28,000 | 140,000 | 55,284,000 | |
37 | Cat Kayu | 2 | Kg | 76,000 | 152,000 | 55,436,000 | |
38 | rak besi | 1 | unit | 8,600,000 | 8,600,000 | 64,036,000 | |
39 | Loster keramik 20x20x8 | 150 | Buah | 22,500 | 3,375,000 | 67,411,000 | |
40 | Kran Air | 8 | Buah | 45,000 | 360,000 | 67,771,000 | |
41 | |||||||
42 |
RAB Bale Lantang Tempat kayu
RAB Bale Lantang Tempat Ngaben | |||||||
Ukuran 8x15 | |||||||
No | Data | Vol | Satuan | Harga | Jumlah | Balance | Keterangan Bahan |
1 | Batako | 6000 | Bh | 2,200 | 13,200,000 | 13,200,000 | |
2 | Batu | 3 | Truk | 1,300,000 | 3,900,000 | 17,100,000 | |
3 | Pasir | 1 | Truk | 900,000 | 900,000 | 18,000,000 | |
4 | Pasir Cor | 2 | Truk | 1,800,000 | 3,600,000 | 21,600,000 | |
5 | Semen | 85 | Zak | 53,000 | 4,505,000 | 26,105,000 | |
6 | Besi 12 TS | 70 | Btng | 96,000 | 6,720,000 | 32,825,000 | |
7 | Besi Gelang | 70 | Btng | 45,000 | 3,150,000 | 35,975,000 | |
8 | Kawat Tali | 6 | Kg | 20,000 | 120,000 | 36,095,000 | |
9 | Balok 10x6 | 90 | Btng | 180,000 | 16,200,000 | 52,295,000 | |
10 | Usuk | 210 | Btng | 80,000 | 16,800,000 | 69,095,000 | |
11 | Reng | 15 | Ikat | 425,000 | 6,375,000 | 75,470,000 | |
12 | Ris | 32 | Btng | 105,000 | 3,360,000 | 78,830,000 | |
13 | Panggal | 16 | Btng | 75,000 | 1,200,000 | 80,030,000 | |
14 | Tatak Jagut | 16 | Btng | 70,000 | 1,120,000 | 81,150,000 | |
15 | Besi Paku | 40 | Kg | 20,000 | 800,000 | 81,950,000 | |
16 | Ikut Cledu | 4 | Bh | 45,000 | 180,000 | 82,130,000 | |
17 | Mudra | 2 | Bh | 50,000 | 100,000 | 82,230,000 | |
18 | Baut 25 cm | 29 | Bh | 15,000 | 435,000 | 82,665,000 | |
19 | Baut 15 Cm | 24 | Bh | 10,000 | 240,000 | 82,905,000 | |
20 | Raab Pres Mini | 7150 | Bh | 1,500 | 10,725,000 | 93,630,000 | |
21 | Subeng | 350 | Bh | 2,600 | 910,000 | 94,540,000 | |
22 | Cat Raab | 5 | Klng | 200,000 | 1,000,000 | 95,540,000 | |
23 | Cat Ris | 5 | Klng | 75,000 | 375,000 | 95,915,000 | |
24 | Air | 20 | M3 | 15,000 | 300,000 | 96,215,000 | |
25 | Benoh | 135 | Bh | 3,500 | 472,500 | 96,687,500 | |
26 | Triplek Begesting | 8 | Lmr | 105,000 | 840,000 | 97,527,500 | |
27 | Usuk Begesting | 80 | Btng | 36,000 | 2,880,000 | 100,407,500 | |
28 | Pekerja total | 1 | ls | 67,000,000 | 67,000,000 | 167,407,500 | |
167,407,500 | |||||||
JUMLAH TOTAL | 167,407,500 | ||||||
RAB Bale Lantang Tempat Ngaben Baja
RAB Bale Lantang Tempat Ngaben | |||||||
Ukuran 8x15 | |||||||
No | Data | Vol | Satuan | Harga | Jumlah | Balance | Keterangan Bahan |
1 | Baja IWF 150 6m | 22 | Btng | 1,176,000 | 25,872,000 | 25,872,000 | |
2 | Hollow 6x4x1,4 | 74 | Btng | 278,000 | 20,572,000 | 46,444,000 | |
3 | Reng baja ringan | 90 | Btng | 38,000 | 3,420,000 | 49,864,000 | |
4 | Genteng metal berpasir | 372 | Btng | 38,000 | 14,136,000 | 64,000,000 | |
5 | Baut m14x45 | 120 | Buah | 8,400 | 1,008,000 | 65,008,000 | |
6 | Sekrup Gypsum | 2232 | Buah | 155 | 345,960 | 65,353,960 | |
7 | Driling 25 | 900 | Buah | 550 | 495,000 | 65,848,960 | |
8 | Pemugbug bali | 132 | Buah | 8,500 | 1,122,000 | 66,970,960 | |
9 | Celedu | 1 | Set | 240,000 | 240,000 | 67,210,960 | |
10 | Mudra | 2 | Set | 120,000 | 240,000 | 67,450,960 | |
11 | Cat Minyak | 16 | Kg | 68,000 | 1,088,000 | 68,538,960 | |
12 | Thiner | 24 | Liter | 19,000 | 456,000 | 68,994,960 | |
13 | Cat Genteng | 1 | Galon | 85,000 | 85,000 | 69,079,960 | |
14 | Kawat Las Mig | 2 | roll | 450,000 | 900,000 | 69,979,960 | |
15 | Besi Ulir 13 cakar | 36 | Btng | 135,000 | 4,860,000 | 74,839,960 | |
16 | Besi beton polos 6mm | 22 | Btng | 33,000 | 726,000 | 75,565,960 | |
17 | List plang lengkap terpasang | 54 | M1 | 245,000 | 13,230,000 | 88,795,960 | |
18 | Cat Lisplank mowilek | 5 | Kg | 67,000 | 335,000 | 89,130,960 | |
19 | Pasir | 3 | Truk | 950,000 | 2,850,000 | 91,980,960 | |
20 | Batu kali | 2 | Truk | 1,200,000 | 2,400,000 | 94,380,960 | |
21 | Semen | 65 | Zak | 52,000 | 3,380,000 | 97,760,960 | |
22 | Triplek Begesting | 8 | Lmbr | 105,000 | 840,000 | 98,600,960 | |
23 | Usuk Begesting | 80 | Btng | 36,000 | 2,880,000 | 101,480,960 | |
24 | Paku 5cm | 5 | Kg | 15,000 | 75,000 | 101,555,960 | |
25 | Air | 20 | M3 | 15,000 | 300,000 | 101,855,960 | |
JUMLAH TOTAL | 101,855,960 | ||||||
26 | Pekerja total | 170 | ls | 425,000 | 72,250,000 | 72,250,000 | |
174,105,960 |